top of page
  • Writer's pictureMelbourne Quantity Surveyors

CASE STUDY - EXPERT WITNESS PROJECT

Dispute Resolution Greater Shepparton (Value $700,000)



The local council planted trees close to a heritage listed building, which resulted in much of the moisture from the surrounding ground being drawn up by the trees. This caused the footings to drop and the building to shift. We were engaged by the owners of the building to provide expert witness costings and related construction techniques associated with the rectification works. We also provided the costs related to moving the business out of the building and into a temporary facility during the completion of the rectification works. This report formed an important part of the evidence used in their damage’s lawsuit.



THE CHALLENGES


During the project, we faced several challenges, including:

  • Costs associated with rectifying a heritage listed building: Costing heritage listed buildings can be difficult. They can be built using questionable construction techniques that – whilst standard in a bygone era – don’t comply with today’s standards. This means that sometimes the visible damage doesn’t reflect the extent of the underlying damage which can be far greater. Also, repairing this damage can be very expensive and highly labour-intensive, with specialised repair techniques needing to be used. Ultimately, these costings can be difficult to price accurately.

  • Costs associated with moving the business into temporary facilities during construction: As part of the lawsuit, we had to provide an estimate for temporary structures and services to allow the business to function as it normally would during the construction period.

  • Cross-examination of all reports and costings by an expert witness engaged by the defendant: The defendant employed an expert witness to defend their case. He would cross-examine our reports and costings and provide evidence to the contrary. This made a difficult task all the more intensive knowing that every single one of our assumptions and estimates had to be incontrovertible, knowing they would be tested and cross-examined.

THE SOLUTION


This project required extensive analysis of the structural engineer’s report to document the proposed works that required rectifying. We conducted a thorough site visit confirming the damage and proposed works to help with any assumptions that needed to be made. Including:

  • Visiting the site and comparing the structural engineer’s recommendations for rectifications with the on-site damage. We then prepared a report stipulating the cost of works to rectify the damage based on the structural engineer’s recommendation. This helped outline the outstanding amount owed by the defendant for reimbursement to the client.

  • Providing a detailed cost report to provide the temporary services (including kitchen, storage, temporary access and services). The report helped the client determine the associated costs of setting up the temporary facilities and whether it was financially viable to go through with this process or simply close the business during the construction period.

  • Attending mediations with the defendant’s expert witness to assess and negotiate the differences between the two estimates. This was an attempt to come to an agreement outside of court, but as the cost variance was too great, we were not able to come to a resolution.

  • Providing expert witness advice and consultation during the client’s legal proceedings to recover the outstanding amount.

  • Attending the court hearing as an expert witness, justifying our estimates and methodology in a court of law.

  • Providing expert witness advice and consultation during the client’s legal proceedings to recover the outstanding amount.

FINAL RESULTS

Going into the court hearing, the defendant had agreed they were liable for the damages. The court hearing determined the acceptable amount in damages for the plaintiff to receive.


The defendant’s expert witness estimate was less than $100,000 for the proposed recommendations set out in the structural engineer’s report. The client also engaged a builder who had priced the same works at approximately $350,000. This figure was the basis of the client’s claim to which the client was seeking the full amount.


Our independent assessment of the recommended heritage restoration works, based on our experience, was in the order of $750,000; this was $500,000 more than the $350,000 the client was perusing from the defendant, an undeniable variance.


The judge ruled in favour of our client for a total slightly over $700,000 for the recommended works and temporary services.


In this case, based on our previous experience with heritage listed buildings and their repair costs, the judge ruled unquestionably in favour of our reports and estimates of costs in almost all instances. The outcome was far better than we could have expected.



For more information about quantity surveyors, call us on (03) 9068 3950 or email us at info@melbourneqs.com.au




bottom of page